2026 Evacuation Route Clearance
Project type: Evacuation Route Clearance
Location(s): Town of San Anselmo, Town of Fairfax, Town of Ross
Streets: Upper Road (Ross), Spring Grove Ave (San Anselmo), W Hillside (San Anselmo), Upper Toyon (Ross), Oak Ave (San Anselmo),
Status: Completed
Who it benefits:
-Directly benefitted many homes by adding to their defensible space
-Emergency responders
Resident communications:
-notification letters sent to residents
CEQA documentation: Central Marin Zone Evacuation Route Core Project CEQA
Scope of work:
These projects focused on trimming individual tree limbs, shrubs, and other vegetation that overhangs the roadway. No mature trees were removed unless deemed a safety hazard by a certified arborist and/or fire officials who determined that removal was the only safe option.