Center Boulevard

Project type: Evacuation Route Clearance

Location(s): Town of San Anselmo, Town of Fairfax

Impact:

Total fuel removed: roughly 312 cubic yards of chipped, raked and cut vegetation 

-This is equivalent to a football field covered in a layer 0.2 inches deep or a cube that is the height of a 2 story house

Length treated: 1 mile.

Who it benefits: 

-Directly benefitted 228 homes by adding to their defensible space

 -Thousands of people that will be evacuating down this road in the event of a fire

-Emergency responders

Resident communications: 

-3 public meetings

-Multiple newsletter postings

-705 notification letters sent to residents 

CEQA documentation: Central Marin Zone Evacuation Route Core Project CEQA

Scope of work:

This project focused on trimming individual tree limbs, shrubs, and other vegetation that overhangs the roadway. No mature trees were removed unless deemed a safety hazard by a certified arborist and/or fire officials who determined that removal was the only safe option.  

 

Before and after photos: