Center Boulevard
Project type: Evacuation Route Clearance
Location(s): Town of San Anselmo, Town of Fairfax
Impact:
Total fuel removed: roughly 312 cubic yards of chipped, raked and cut vegetation
-This is equivalent to a football field covered in a layer 0.2 inches deep or a cube that is the height of a 2 story house
Length treated: 1 mile.
Who it benefits:
-Directly benefitted 228 homes by adding to their defensible space
-Thousands of people that will be evacuating down this road in the event of a fire
-Emergency responders
Resident communications:
-3 public meetings
-Multiple newsletter postings
-705 notification letters sent to residents
CEQA documentation: Central Marin Zone Evacuation Route Core Project CEQA
Scope of work:
This project focused on trimming individual tree limbs, shrubs, and other vegetation that overhangs the roadway. No mature trees were removed unless deemed a safety hazard by a certified arborist and/or fire officials who determined that removal was the only safe option.
Before and after photos: